A realistic four-week path for a business that has never bid on public work. It assumes you already sell the service commercially — this is about government paperwork, not about learning the trade.
Week 1 — Make yourself eligible
| Day | Action | Output |
|---|---|---|
| 1 | Decide the trade and the three counties/cities you will actually serve | A one-line scope statement |
| 2 | Register in the state portal; choose commodity codes from real solicitations in your trade | Registration confirmation |
| 3 | Register with your county, city and school district purchasing offices | Three vendor numbers or forms submitted |
| 4 | Request insurance certificates; confirm the limits the typical notice asks for | Certificate PDF in hand |
| 5 | Write the one-page capability statement: what you do, where, insurance, references | The document you will reuse forever |
See Registration and bidder lists and Commodity codes.
Week 2 — Read the market before bidding
| Day | Action |
|---|---|
| 8–9 | Search the state portal by keyword and by class code; note every open notice in your trade |
| 10 | Email the county/city purchasing office: "what contracts in [trade] do you have, and when do they expire?" |
| 11 | Read two solicitations in full, without bidding — one IFB, one RFP |
| 12 | Write down the five things every notice asks for (that list becomes your checklist) |
Read Reading a solicitation before day 11; it will halve the time.
Week 3 — Choose one and build the response
Pick a notice that passes four tests: you can deliver it, the insurance requirement is one you carry, no licence or bond is required, and it closes at least seven days away.
| Day | Action |
|---|---|
| 15 | Build the compliance checklist: every requirement, quoted, with a column for where it is answered |
| 16 | Price it. Cost build-up, not a gut number: Pricing an arbitrage bid |
| 17 | Draft the response against the checklist, in the buyer's format |
| 18 | Get the quotes that support your price in writing (supplier or sub) |
| 19 | Second-person review: tick the checklist again, line by line |
Week 4 — Submit, then verify
| Day | Action |
|---|---|
| 22 | Submit 48 hours early, then confirm receipt (portal confirmation or an email reply) |
| 23 | Re-download the notice; check for addenda issued in the last 48 hours |
| 24 | Submit the final version if anything changed |
| 25–30 | Do not wait idle: open the next two notices and repeat with the checklist you now have |
What a realistic outcome looks like
- First-time bidders win a small fraction of what they submit — assume the first two or three are practice.
- The prize from this month is not the contract; it is the compliance packet, the checklist and the registration set, which make every subsequent bid a two-hour job instead of a two-week one.
- The fastest win usually comes from the quote tier (under the formal threshold) where the purchasing office already knows your name after week 1.
The three things that make week 1 worth doing properly
- Codes. Registered under the wrong class, you will search for a year and conclude the state does not buy your service.
- Insurance. The certificate takes days; discovering it is short on submission day costs the bid.
- The capability statement. It is the document you will paste into every RFP introduction for the next decade. Write it once, well.